Experienced Completions / Commissioning Lead Engineer with a long and proven history, and over 20 years experience working in various international heavy industrial, oil & gas, power generation and pharmaceutical projects.

Highly professional with strong communication and leadership skills. Well organized with flexible and common sense approach towards problem solving. Works independently under pressure and is adaptable with multinational personnel at all levels, under different environmental conditions.

Proficient technical author of commissioning procedures, and compilation of commissioning & handover dossiers.

Fully conversant with Piping & HVAC P&IDs / Isometrics and their fabrication, erection, inspection and testing.

Capable in the review of process P&ID's and construction turnover packs, piping and Mechanical test packs, Piping Isometrics and creation of system boundary drawings, associated with oil and gas, Pharmaceutical and chemical process systems.

Co-ordination and scheduling of pre-commissioning and commissioning activities including vendor support.Supervision and co-ordination of large local crews of craft labour to facilitate construction completion through to smooth start up.

Self motivated and pro active with a bias towards problem solving, in extreme environments where a quick solution is required to progress the works.

Work History

Work History
Sep 2011 - Present

Mechanical Commissioning Lead

Shell Iraq Petroleum Development - Majnoon FCP Project

Coordinating the commissioning activities, particularly for rotating and static equipment, both in the planning and execution phase. Assuring that the project scope is divided up into systems that are defined in a manner that will support ease of commissioning. Work with the commissioning team to set priorities for system turnover that allows for productive simultaneous operations (Simops) that allows for safe commissioning of systems while the construction contractor completes and turns over the remaining systems. Assure that the System Commissioning Procedures are developed, approved, and finalized per the planning schedule and include the appropriate content and detail to assure safe and thorough commissioning. Assuring that the Commissioning execution plan includes the materials, special tools, and vendor support for a safe and productive pace. Assuring that the commissioning staffing plan has the correct number of persons with the appropriate skills to execute the commissioning work. Represent the Commissioning team in key meetings with interfacing departments (Operations, Engineering, and Construction etc.). Supports Flawless Project Delivery objectives which include managing and monitoring various quality metrics. Provide support for the Project Quality Audits. Supporting project Factory Acceptance Testing (FAT) including: reviewing procedures, assigning resources, periodically attending FAT, and adjusting commissioning scope to integrate FAT successes and deficiencies. Tracking and adjusting commissioning execution schedule. Working with engineering and operations department to promptly find the preferred alternative for alleviating issues discovered during commissioning. Lead the on-site (module yard in Dubai – Site based in Iraq) commissioning activities, including resource management, schedule coordination, materials/tools/vendor support, system/equipment troubleshooting, and adjusting plan due to resource issues. Assisting in the development of commissioning spare parts listing and quantities. Interfacing effectively with project personnel (project leadership and engineering staff), operations team, contract field construction personnel, and vendor support staff. Operating in a team environment and able to quickly understand the roles of the interfacing teams, developed quick relationships, and worked effectively to assure that the commissioning work integrates well in the overall project plan.

Jan 2011 - Sep 2011

Completions / Commissioning Engineer

Exxon Mobil – Arkutun-Dagi Field development, Sakhalin 1 – Houston, then based in DSME Shipyard, Korea

The project is a Gravity Based Structure (GBS) and Topsides designed/engineered in Houston, being constructed in South Korea and will be installed as a working platform off-shore Sakhalin Island.I was, up until May 2011, officiating in the role of Exxon Mobil company representative in Contractors office as a member of a multi-functional project execution team, responsible for interface with the engineering, procurement, operations and maintenance personnel, specifically relating to utility systems.Supporting the development of packaged equipment deliverables, including support of the coordination efforts for the downstream contractor. Reviewing work done by the contractor. Identifying the key issues/risks and involving Subject Matter Experts (SME’s) as required. Coordinating the efforts of the SME’s, reviewing specifications, RFQ’s etc.Providing direction to the downstream contractor in the design development/procurement of packaged equipment, preventative maintenance philosophy, equipment layouts and maintenance access.Providing continuity of discipline efforts through detail design as well as assisting in any estimate, scheduling and project assurance activities. Participating in HAZOP, vendor selection, vendor documentation reviews, Engineering Inspections and Factory Acceptance Tests (FAT’s).Committed to the development and implementation of a safe working environment for everyone on the project and the continuing establishment of an incident and injury free culture.The role developed into a System Owners / Commissioning Engineers role where I was based in the fabrication yard in Korea, and where the relevant assigned systems are closely monitored through Construction Mechanical Completion and then taken through pre-comm and full Dynamic Commissioning.

Feb 2009 - Oct 2010

Commissioning Engineer

SHELL – Corrib Onshore Gas Terminal, Bellanaboy Bridge, Glenamoy, Ballina, Co. Mayo, Ireland.

Technical writing of procedures and compilation of commissioning dossiers for review and approval by SEPIL, with the subsequent follow up and field / practical completion of same for handover to SEPIL OPS.

Witnessed and assisted in the pre-commissioning of systems through close liaison with construction and subcontractor personnel. Monitored subcontractor’s implementation of pipe cleanliness controls, flushing, blowing, reinstatement and other activities. Writing and compilation of blowing procedures and directing the implementation of same.

Reviewed the contractors ductwork installation to all buildings and witnessed testing of same.

Reviewed HVAC Controls strategy and was involved in the implementation of design changes.

Ensured all HVAC equipment was put through its paces, performance wise and ran satisfactorily to specification.

Ensured all pre-commissioning activities were completed to the necessary quality in accordance with the system pre-commissioning work plans.

Officiated in the role of N2/He Leak Test Superintendent, review and approval of Test packs, system sequence co-ordination and field supervision at time of testing.

Carried out and completed record sheets for equipment tests, blind isolations, temporary closures, internal inspections, safety checks, and media loading.

Reviewed systems for operability and operational safety, and where necessary proposed punch queries for supervisory review.

Carried out commissioning static and dynamic tests, and signed off checklists and method statement records to confirm the activities had been satisfactorily completed.

Coordinated the simultaneous activities of vendors, subcontractors and disciplines during these tests to enable maximum functionality of equipment to be demonstrated.

Monitored the safe conduct of the work and ensuring the work permit safety conditions are being met. Applied commissioning standard safety measures to all work.

Started up and operated equipment during testing and in early utility service, until the system was turned over from commissioning to operations.

Specific systems taken through all pre-comm and through full commissioning include all Fire-fighting systems, inclusive of Fire water Pumps and Ring main, foam skids, deluge skids / systems, hydrants, foam monitors, foam pouring systems ( tanks ) etc.

Also under my scope were all HVAC, Oily Water Collection, Open Drains, HP/LP Flare and HP/LP Fuel Gas Systems. All Static / Rotating equipment associated with these were taken through pre-comm and dynamic commissioning, vessel / tank inspections, pump alignments / runs etc.

Aug 2007 - Feb 2009

Commissioning Engineer

Sakhalin Energy Investment Company ( SEIC ) SHELL

Duties / Responsibilities similar to above project.

Specific systems taken through all pre-comm and through full commissioning include all Fire-fighting systems, inclusive of foam skids, deluge skids, hydrants etc.

Also under my scope were all MEG Systems, HVAC, Diesel, Nitrogen, Gas Dehydration and the Feed Reception Systems. All Static / Rotating equipment associated with these were taken through pre-comm and dynamic commissioning, vessel / tank inspections, pump alignments / runs etc.

Submission to our Completions department of all relevant documentation to facilitate a smooth transition to our Operations team

2003 - 2007

Construction Manager - 4 projects - Pfizer Pharmaceutical, Guidant, Athy International Concentrates (Coca Cola), Beaumont Hospital

Dornan Engineering Ltd.

Managing installation of all Mechanical and HVAC works inclusive of the following:

Dornan Lead for Co-ordination, Progress meetings and HSE meetings with the Project management team.

Liaise with vendors and sub-contractors for progress and material and equipment procurement.

Supervised the fabrication, erection, inspection and testing of various pipe systems as per isometrics and GA’s.

Supervised the fabrication, erection, inspection and testing of various duct systems as per isometrics and GA’s.

Supervised the timely shutdown of equipment and services to allow ‘hot’ tie-ins to existing services as this was an extension to a live production plant.

Ensured the timely completion of shop fabrication as dictated by schedule.(Pipe and Duct)

Cross checked Isometrics with P&ID’s, referring to the relevant codes, standards and specifications.

Co-ordinated the setting out, installation and alignment of mechanical/HVAC equipment.

Inspection of all Static Equipment and verification it conformed to spec. Heavily involved in preparation of RFI’s and STQ’s and implementing their consequence. Punch listing. HSE walkdowns.

Preparation of test packs in line with Site QA/QC and Turnover requirements. Preparation of As-built drawings.

Piping system handover documentation

2002 - 2003

Mechanical / Piping Superintendent

B.M.D. & Co. Ltd.

Wyeth Medica, Bio-technology Campus, Clondalkin, Dublin, Ireland

2000 - 2001

Mechanical / Piping Superintendent - 2 projects

Kentech Int. Ltd.

Karachaganak Development Project – Unit 3, Aksai, Kazakhstan

Texaco. - North Buzachi Oil Facility, Aktau, Kazakhstan

1998 - 2000

Mechanical / Piping Supervisor - 3 projects

Dornan Engineering Ltd.

 Edenderry Power Plant, Edenderry , Co.Offaly, Ireland

 Elan Pharmaceuticals, Athlone , Co , Westmeath, Ireland

 Beverages Plant, ‘The Coca-Cola Company’, Killala Road, Ballina Co. Mayo.

1996 - 1997

Mechanical / Piping Supervisor - 3 projects

Kentech Int. Ltd.

 Renaissance Capital (Bank), Moscow, Russia

 Domodedovo Airport, Moscow, Russia.

 Office and Shopping Complex, Manezh Square, Moscow, Russia.



On the job training

SHELL - EDS (Engineering Data System)

Flawless Project Delivery (24 - 26 April 2012)


Foster Wheeler Docstore & Fintail Engineering systems

Russian Safety Training in Oil & Gas and Russian Labour Protection Training

Bechtel Info-works Engineering

IA – Isolating Authority – ISSOW PTW

AGT - Authorized Gas Tester

CSEConfined Space Entry (including use of full B.A.)

2010 - Present

City & Guilds

OPITO - Petroleum Processing Technology ‘City & Guilds’ Certificate in ‘Gas Dehydration’

OPITO - Petroleum Processing Technology ‘City & Guilds’ Certificate in ‘Oil and Gas Separation’