• rali1785@gmail.com

Rashid Ali

Civil Engineer

Summary

Over 13 years relevant experience in providing Construction Field on Various civil engineering projects Like High Rise Building. Commercial Building, Power Plant. Villas

Work History

Work History

Assistant Construction Manager

Jan 2012 - Present
Al Samrya Trading & Contracting

Project- Samrya Quartier Hotel (5 Star), 3B+G+07

  • To lead, control, manage, coordinate and delegate duties for a multicultural and multinational Team of SEs, MEP Site Engineers, HSE, QA/QCs, Planning Engineers, Structural Engineers,  in order To build a five-start-hotel of area (15000M2).3B+G+7floor.
  • Proposed excellent idea which will create solution to problem.
  • Review proposal submitted by sub-contractors as a remedial measures in case problem arises.
  • Review and approved subcontractor invoice, Material Monitoring Record, Material Delivery Record. 
  • Prepare report on schedule of work in advance and accomplishment of project
  • Raised/Prepared Inspection Request and Request for Information to consultant time and location of inspection.
  • Prepare Daily & Weekly Progress Report & Weekly Look Ahead schedule

Project  Engineer

Mar 2010 - Jan 2011
Hyundai Heavy Industries

Project-- Sabiya CCGT Power Plant(2175 MW)

  • Involved in the construction of all facilities. Central Control Building. Local Switchgear Building#1, 2, 3. Gas & Steam Turbine Foundation. Cable Trench, Pipe Trench, Pipe Sleeper at Fuel Tank area. HRSG (Heat Recovery Steam Generator) Foundation.
  • Prepare material submittals for client/ consultant approval as per the project specifications and drawings prior to the procurement of materials.
  • Raised/Prepared NFI (Notice for Inspection) consultant time and location of inspection.
  • On daily basis visit the work site and check, monitor and make sure the work done is in compliance with project approved QA/QC plan.
  • Preparing daily report weekly report & weekly progress photograph.
  • Follow up the supplier and independent laboratory for QA/QC reports and tests results and prepare complete package prior to offering for consultant’s inspection.
  • Promote safe site working practices with working items

Section Manager

Feb 2008 - Jul 2009
Al Dar Laing O Rourke
  • Project-- Al Raha Beach Project (Al Zeina) Abu Dhabi
  • Supervised the Site construction activities, review drawings preparing daily & weekly work Report.   Weekly look ahead program. Attending site progress meeting.
  • Follow up the supplier and independent laboratory for QA/QC reports and tests results and prepare complete package prior to offering for consultant’s inspection.
  • Prepare manpower and equipment schedule for particular site
  • Review all drawings and specification related to civil and structural.
  • Proposed excellent idea which will create solution to problem.
  • Review proposal submitted by sub-contractors as a remedial measures in case problem arises.
  • Prepare report on schedule of work in advance and accomplishment of project
  • Raised/Prepared Inspection Request and Request for Information to consultant time and location of inspection.

Project Engineer

Mar 2004 - Nov 2007
Imperial Trading & Contracting Company   
  • Checking finishing works such as, block laying, plastering, tile and marble installation, ceiling, painting partition walls, cabinet installation, waterproofing ,painting, excavation, compaction test (FDT) steel reinforcement and other items related to architectural, civil and structural works. etc.
  • Prepare manpower and equipment schedule for particular site
  • Review all drawings and specification related to civil and structural.
  • Proposed excellent idea which will create solution to problem.
  • Review proposal submitted by sub-contractors as a remedial measures in case problem arises.

Prepare report on schedule of work in advance and accomplishment of project

Senior Site Engineer

Nov 2001 - Oct 2004
Naresco Contracting Company LLC
    • Prepare manpower and equipment schedule for particular site
    • Review all drawings and specification related to civil and structural.
    • Proposed excellent idea which will create solution to problem.
    • Review proposal submitted by sub-contractors as a remedial measures in case problem arises.
    • Prepare report on schedule of work in advance and accomplishment of project.

Education

Education

B.C.E

1998
University Of Banglore

Certifications

Certifications

Risk Assessment & Method  Statement Course 

BHB Safety Specialist Unit 2, Old Ballyrobin Road Antrim North Ireland BT414TJ

Certificate#---BHB/1489/161/1652               

 

Skills

Skills

SOFTWARE TOOLS

Ms Word, Excel, Ms Office, Asite, Aconex, AutoCAD, 3D (Smart Plant Review) Operation, Primavera-Basic.