1. Maytas Infra Ltd:

After 6 month service, got promoted from Executive Planning Engineer to Assistant Manager.

What I can bring to your Organization?

  •  Provide expertise in the field of Project Planning & Management
  •  Undertake challenging job under diverse conditions

Summary

Project Planning and Management - Well versed in Buildings and Power Plant Project

  • Scheduling
  • Resource & Cost Estimation
  • Tracking and Monitoring of Project for on-time and Within Budget execution
  • Earned Value Management
  • Risk Management
  • Vendor and Client Negotiations

References

Sabyasachi Bir

  • Currently he is my senior and he can be reached to know my work profile.

Krishna Mohan Vissapragada

  • During my Maytas Infra Ltd tenure he was my reporting manager . He can be reached to know my work profile.

Girish D

  • During my Sobha Developers tenure as a Site Planning Engineer he was my reporting manager. He can be reached to know my work profile.

Work experience

Mar 2009Present

ASSISTANT MANAGER

Zelan Berhad Malaysia
  • Tracking and Monitoring of Power Plant project - 2 x 300 MW
  • Revision of baseline schedule for enhanced tracking
  • Generation of S-curves and project progress reports
  • Creation of detail schedule of 3 x 350 MW Coal fired Power Plant
Feb 2008Feb 2009

Assistant Manager - Project Planning & Management

Maytas Infra Ltd
  • Created detail Level 3 schedules for Building Project using Primavera
  • Estimation of project resources and cost
  • Performed Tracking and Monitoring of Building projects
  • Responsible for Central Planning-Buildings Sector as a Team Leader
  • Performed training of site personnel in Primavera for concepts and practical application
  • Created standard work output norms for Labor and Material in detail applicable for Building Project
  • Assisted in creation of work output norms for Roads and Railways
  • Initiated scheduling of Power plant project
Feb 2007Feb 2008

Planning Engineer

Sobha Developers Ltd
  • Responsible for planning and monitoring of a 14storey Luxurious Residential Building project
  • Underwent training in Primavera - Project Planning module
  • Created schedule for the building project
  • Performed tracking and monitoring of the project
  • Delay analysis and make-up plan on fortnight basis
  • Estimation of monthly Material and Labor requirement
  • Calculation of cost of material requirement and consumption for cash flow reports
  • Provide guidance to Jr. Planning Engineer in site planning activities
Jul 2006Jan 2007

Site Engineer

Sanghi Engineers
  • Responsible for execution of site work of 4 storey Residential Building Project
  • Creation of Daily Progress Report (DPR)
  • Estimation of material consumption and Labor requirement projection

Labor and Material Output Norms

Education

20022006

Bachelor of Engineering

KDK College of Engineering
  • Percentage Scored: 65.76% (1st Class).
  • Graduated in Civil Engineering (Four years) without arears throughout. Subjects related to PPM were of keen interest.
20002002

Higher Secondry School Certificate

Hislop College
  • Percentage Scored: 60.00% (1st Class).

Skills

Autocad
Primavera
I can conduct Training and implementation of Primavera -(P6).

Certifications

2006Present

National Technical Paper Presentation

YCC College of Engineering
2006Present

National Technical Paper Presentation

KDK College of Engineering
2003Present

National Technical Paper Presentation

IIT Madras
20082009

Teach India

Times of India - Bhumi