Construction/Structural Engineer
PT.Gunanusa Utama Fabricators
Bongkot Field Development Phase 4A
PTTEP - QPS Living Quarter Platform with four legs 3350 MT, QPS jacket 650 MT, Flare tripod jacket 250 MT and its 1300 MT piles
As Transportation & Installation Coordinator
Mar 2011 – June 2011
Job Description :
-Technical assistance for T&I preparation onshore..
-Coordinate with Heerema Marine Contractor (HMC) as T&I Subcontractor (use SSCV HERMOD).
-Review HMC procedures and design of installation aids requirement.
-Coordinate the work with all parties, i.e fabrication coordinator, load out coordinator, marine department, etc
Involved in some bidding
As Senior Structural/Method Engineer
Feb 2011 – Mar 2011
-GSPC - India – Den Dayal West – Process cum Living Quarter Platform – EPC-1B (Process platform, Tripod flare, bridge)
-PTTEP – Myanmar, Zawtika development project, Phase 1A, EPCIC for WP1, WP2, WP3 (three wellhead platform)
-TOTAL E&P Indonesie, Sisi Nubi 2B and Peciko 7B Project Greenfield. (three wellhead platform)
Job Description :
-Technical tender preparation and prepare MTO for bid.
-Prepare method statement of fabrication, load out.
-Prepare method of heavy equipment installation.
ONGC - Mumbai High South Re-Development Phase-2 Project
ICP-R Process Plaform with four legs, consist of9000 MT Topside (Modular Construction) and Bridge 576 MT.
As Construction Engineering Coordinator
Jun 2009 –Jan 2011
Job Description :
-Prepare master document register (MDR) and man power loading in earlier project
-Provide weekly report for production engineering status.
-Distribution task job to each discipline lead engineer (Structural, Piping, E/I, Precom & Com.).
-Coordinate the construction engineering activities information flow.
-Designing, implementing, project on schedule in engineering view.
-Interface with engineering design company to speed up the progress.
-Review load out, ballasting and sea fastening design procedure and coordinated with T&I contractor (Heerema Marine Contractor) to ensure the all installation issue.
-Prepare equipment installation method to suit the ETA date at Yard.
-Prepared project close out report (As built drawing, etc)
TOTAL E & P INDONESIE – Tunu Field Development Project Phase 11 South – EPSC 1 & 2
4600 tonnes of South Compression Platform (SCP) with 16 legs & 2700 tonnes of South Manifold Platform (SMP) with six legs,
As Lead Structural Engineer
Feb 2007 –May 2009
Job Description :
-Review fabrication and erection procedure.
-Distribution task job to each structural engineer.
-Prepared procedure and expedited heavy equipment transportation from vendor to the yard.
-Prepared heavy lifting, load out, ballasting and sea fastening procedure.
-Supervise and examine the proceeding shop drawing, cutting instruction and material take off.
-Prepared Yard Technical Query.
-Analyze and supervise the proceedingsite fabrication performance.
-Supported site installation activities (float over installation method)
-Hook up activities
TOTAL E & P INDONESIE – Sisi Nubi Field Development Project – Phase 1/EPSC 1
3500 tonnes of Production Separation Platform (SNPS) with 12 Legs.
BP – Tangguh Gas Production Facilities (GPF) Project
1200 tonnes of Wellhead Plaform Topside (2 nos) and 1900 tonnes of Jacket (2 nos) with six legs included 1300 tonnes piles.
As Structural/Construction Engineer
July 2006 –Jan 2007
Job Description :
-Develop engineering procedure for shop assembly, erection and yard fabrication
-Develop and supervise recommended engineering procedure including structural analysis, local strength check and rigging arrangement for preparation and execution of stacking, erection and jacket roll-up operation (heavy lifting operation)
-Develop load out, ballasting and sea fastening design procedure.
-Develop and supervise the yard development prior project started.