Mar 2013 - Present

Project Engineer

Ringland-Johnson Construction

Woodward Rock Cut Campus (Loves Park, IL)  $110 million

  •   Estimating and bid package preparation, pre-construction
  •   Submittals, RFI's, material tracking, change orders
  •   Achieved an average 10% net profit on self performed CO's
  •   Managed solo night work for 7 weeks, main contact for emergencies
  •   Produced, distributed, and managed a 1500+ item punch list

ComEd Lincoln Center 2 Generator (Oak brook Terrace)  $1.9 million

  • Owner Rep/Construction liaison
  • Produced weekly MOP (method of procedure) for power shutdowns
Jan 2012 - Mar 2013

Project Engineer

F.H. Paschen, S.N. Nielsen

I-57 / Route 13 Interchange Reconstruction (Marion, IL)  $42 million

  •   Project specific concrete take-offs
  •   Hand sketched steel lift plans for IDOT approval
  •   Managed coordination and install of 4 million dollar sign package
  •   Weekly projections, adjusted install methods based on percentages

Chicago Public Schools (Chicago, IL)  $250k - $5 million

  •   Submittals, RFI's, Closeout

Education

Education
2007 - 2011

B.S. Construction Management

Bradley University
2012 - 2013

OSHA 30 Card

Sheffield Safety & Loss Control
2013 - Present

LEED Green Associate

USGBC