Managing Director/CEO Managing teams of engineers providing design, maintenance and supervision of telecommunications network rollout, installation of solar photovoltaic power systems, back-up power systems, rural electrification, street lighting, and wind energy projects.

2MVA UPS FOR MMIA & NAIA

2010 - Present
2MVA UPS FOR MMIA & NAIA
IN- ports. TERNATIONAL AIRPORTS, LAGOS AND UPS Size: 2000KVA ABUJA: 900AH@440VDC x 5 Project involved borehole drilling, tank construc- ! CV page! NASIRU MB 5: Solar Rural Electrification Project involved design, procurement, installation Solar Rural Electrification of solar array, batteries, inverters, controllers and

Maintenance Technician

Sep 1982 - 2014
National Television Authority, Jos, Nigeria
Maintenance Technician Repaired electronic equipment-VCRs, colored and B/W monitors, test equipment, etc. Able to use spectrum analyzer, oscilloscope, etc., Experiences and Publications Solar Power Systems Design, Installation and Maintenance(published by Safari Books, Ibadan, Nigeria,) Design and deployment of Nigeria's first Village Solar Power Plant: 7.2kWp Kwalkawlawa Village Solar Power Plant, Sokoto State, Nigeria

Project Manager

Nov 2005 - Dec 2009
ZTE Corporation
Project Manager, Millicom(Sierra Leone) GSM Project Shenzhen, China Undertook the review and evaluation of the prepared Plans and reports for phase 1 of the project. Designed subsequent project plans for phase 2,3, 4&5. Liaised with clients to establish Project Design Briefs and implementation plan including enduser's requirements. Established project delivery strategy and prepared a practical and comprehensive project implementation plans for design and construction that achieved all critical target dates of the Project Master Plan. Pre-qualified design civil works sub-contractors, prepared RFP and invited short listed firms. Selected sub-contractors, prepared, negotiated and designed contracts. Established cost, quality and time control procedures(Project Manual), and monitored its successful implementation throughout the project phases/stages. Established and implemented reporting system for all projectphases/stages. Monitored the implementation of quality assurance control program, with the Design Consultant and in-house CW supervisors. Reviewed all design deliverables, including field surveys, site surveys and tests, for content, quality, value, and adherence to the established Project Development and design contract requirements. Established construction scope of work for the various contracts and particular terms/conditions of construction tenders/contracts. Managed the pre qualification, tender and award of construction packages. Monitored construction progress and recommended recovery measures in case of delays. Reviewed and processed payments/variations/claims and provided recommendations. Provide assistance in Project close out procedures and transition/handover to End Users after PAT, PAC The Phase I project involved the rollout of 57 BTS sites and the cutover of the core network along with two SDH rings in six months. The project was made difficult by the fact that 20 of these sites were existing sites with insufficient floor space to allow for parallel build. Four civil contractors were commissioned for the new sites with one contractor serving as a backup. We had six BTS installation teams. Two managers reported directly to me for the access and core networks respectively. I also had three team leaders for the Access network: Civil works, MW and BTS installation. I set up daily review meetings with key project stakeholders to coordinate the rollout process and ensure that

Assistant General Manager

Apr 2003 - Nov 2005
Kaduna & Zaria Networks(Operations and Maintenance) National Television Authority, Jos, Nigeria
Assistant General Manager, Intercellular Nigeria Plc. Set up the operations and maintenance department of the new network and supervised operations at the

Project Implementation Manager

Dec 2002 - Mar 2003
Kaduna, Maiduguri & Zaria Networks CDMA National Television Authority, Jos, Nigeria
Project Implementation Manager, Networks. Intercellular Nigeria Plc. Supervised teams involved in installation, optimization and commissioning. The network used ZTE

Project Implementation Manager/head

Oct 2002 - Dec 2002
Intercellular Nigeria Plc. National Television Authority, Jos, Nigeria
Project Implementation Manager/Head(O&M), Kano CDMA Network. Team member implementation of CDMA wireless telecommunication networks in Kano, Nigeria. Supervised work teams involved in RF planning, site acquisition, and installation. The network used Motorola EMX5000 switch, Motorola CBSC and 5 Motorola BTS. Microwave links were used for the BTS links while an STM-1 optic fiber link provided interconnectivity to NITEL, MTN and Econet. Hardest part of this project was the interconnectivity with the other PTOs and NITEL as well as Intercellular's other offices. Coordinated project rollout activities and interfaced with the main vendor Motorola as well as subcontractors for power supply and cooling systems. Supervised ATPs and quality assured all technical aspects of the project. After network launch, I served as head of operations and maintenance department. In this role, I supervised maintenance staff and assigned roles, workloads and schedules. I also developed, interpreted and implemented company policies and procedures for the O&M department. I evaluated staff and ensured that staff are trained in complex maintenance activities and are following standard operatingprocedures. Established and monitored schedules for maintaining the performance of all systems; including environmental systems, network and telecommunications systems, and power generation equipment. Also monitored network and system performance; performed physical planning and generated usage statistics. I maintained equipment inventory and prepared analytical and statistical reports on operations and activities. I also ensured that routine maintenance procedures were strictly adhered to. To ease generation of reports and operational logs, I introduced electronic logs which were used not only by the O&M department, but deployed across all departments. This provided filtering of issues from customer care and speeded up problem resolution. Also assisted in the periodic evaluations of subordinates and recommended as well as implemented disciplinary measures as required. Acted as single point of contact for all network related questions and provided information related to projects including resolving problems, handling complaints and providing technical expertise. Interacted professionally with the vendors, contractors and regulatory institutions and maintained effective working relationships with the management team to effectively meet departmental objectives. I performed a variety of field maintenance tasks, including interconnection with PTOs, resolving transmissions problems

Operations Manager

Jan 1999 - Sep 2002
Solarec Engineering Limited National Television Authority, Jos, Nigeria
Operations Manager Engineering project leader providing solar photovoltaic, UPS, Inverter, rural electrification, street lighting, IT and telecommunications expertise, support and leadership to the field teams. Set up support centre and refined field installation teams to create a more quality focussed approach, leading to an increased rollout of successfully completed projects. Handled multi-million naira projects for the Nigerian Energy Commission ranging from water supply to electrification. Designed and supervised solar rural electrification projects for Nasarawa state governments worth over 50 million naira. Coordinated several field maintenance teams responsible for routine maintenance, repairs and monitoring of solar installations. Organised maintenance workshops with Sokoto Solar energy Research Centre to trained technicians from clients on operations and routine maintenance of their equipment. ! CV page!/! 4 18 NASIRU MB

Engineering Manager

Nov 1990 - Dec 1998
Sunrays Electric Company Limited National Television Authority, Jos, Nigeria
Engineering Manager Team Leader, installation and maintenance. Responded to and resolved difficult and sensitive inquiries and complaints; provided user support for solar, network and rural telecommunications systems. Supervised field maintenance technicians. Designed and supervised numerous solar powered systems for rural water pumping, electrification, vaccine refrigeration, communications, etc. Involved in the project cycle to deliver key customer requirements. Also supported marketing activities like trade-shows with solar photovoltaic

Graduate Assistant

Sep 1988 - Jul 1989
Sunrays Electric Company Limited National Television Authority, Jos, Nigeria
Graduate Assistant Graduate Assistant(on NYSC) with Electrical Engineering Department of Auchi Polytechnic Established an electronic training workshop for students