Feb 2012 - Jun 2014

Project Manager

Hassan Marzouq Al otaibi Company For Trading and Contracting
  • Completing some roads in northern boarders (fifth group) with total cost 23.5 millions S.R.
  • Wideining of arar- airport road in northern boarders with total cost 22.5 millions S.R.
Oct 2009 - Feb 2012

Project Manager

Nile For Roads & Bridges
  • Construction upper banha bridge on Nile River (damita branch) in among the regional ring road (badr - elsadat) with total cost 447 millions L.E 
  • Construction upper wasfia bridge on Ismailia canal and its interances in among the road (cairo  - ismailia) with total cost 55millions L.E.
Jul 2007 - Jun 2009

Project Manager

Saad and Said Al-Harbi
  • Abha streets maintainance with 150 Km  length and total cost 30 Million S.R .
  • Ahd rofida valliages with 60 km length and total cost 30 Million S.R .
  • Wadi ben hashbal valliages with 40 km and total cost 20 Million S.R .
Apr 2003 - Jul 2007

Project Engineer

Nile For Roads & Brides
  • El sofia –kafr sakr road with 20 km length.
  • El hosania – san elhagar – el gamalia road with 42 km length.
  • Awlad sakr – san el hagar road with 15 km length.

Education

Education

Skills

Skills

Autocad 2015

Autocad civil3d 2013

Microsoft Office 2010

English Language

Certifications

Certifications
Jun 2014 - Present

PMP EXAM PREPARATION CORSE

CAMP EGYPT