Mar 2016Present

Construction Manager

Egis EAU

Consulting Services for Supervision of Civil Works to be implemented under Irrigation and Land Market Development Project (ILMDP) - Ministry of Agriculture of Republic of Georgia

Lot 1 :Zeda Ru irrigation scheme Main Canal in Kareli Municipality

Lot 2 : Rehabilitation of the Electrical and Mechanical Parts of Kvemo Samgori Irrigation Scheme Right Main Canal and Headworks in Sagarejo Municipality

Lot 3 : Restoration of the Instrumental Monitoring System  of Algeti Water Reservoir Dam and Hydraulic Structures at Tbisi-Kumisi Irrigation Scheme, Rehabilitation of the Main Canal, Water Pipelines in Khaishi and Marabda  Areas

Construction supervision of the Works Contracts.

The Works Contracts are based on World Bank Conditions. Total amount of the Works : Lot 1 -  2.580.000 Euro ; Lot 2 – 3.730.000 euro ; Lot 3 -  5.950.000 Euro

Nov 2013Present

Team Leader

Egis EAU

Millennium Challenge Corporation USA – Millennium Challenge Account Moldova.

Team Leader for the Construction Supervision of the Works Contracts for the Rehabilitation of the Centralized Irrigation Systems along Nistru and Prut River (Criuleni, Lopatna, Jora de Jos, Cosnita, Puhaceni and Roscani, Grozesti, Blindesti, Leova, Chircani and Zirnesti).

The Works Contracts are based on FIDIC – Red Book Contract Conditions.

Total value of the works : 80 million USD

Total pipelines reconstructed : 530 Km.

Total pumping stations rehabilitated : 33 pumping stations with 104 pumps.

Sep 2010Nov 2012

Senior Resident Engineer

EGIS International

TAMIP - Technical Assistance for Municipal Infrastructure Projects.

Senior Resident Engineer of the Supervision Phase of 11 Projects financed by European Union and 3 project financed by the Ministry of Local Self Government of Republic of Macedonia.

Beneficiary of the Projects are 14 Municipalities of the Republic of Macedonia.

The Works Contracts are based on PRAG Contract Conditions.

Jun 2008Sep 2010

Project Manager

OTV (VEOLIA Group)

Balchik Water Supply and Sewerage and Sewerage Network Extension and Rehabilitation

Financing authority: ISPA Measure EU Funds & Ministry of Environment and Water

Contract value (Euro): 8.658.000

Water Supply Component

Construction of a main and secondary water supply pipelines in overall length of approx. 38.000 m’ of HDPE 100 water mains diameter from DN 90 to DN 400 mm, MDPE 80 water mains diameter from DN 32 to DN 75 mm and execution of approximately 3.000 new service house-connections.

Rehabilitation of existing Reservoir - Construction of Chlorination Station - Construction of Booster Station

Construction of Air Valve & Isolation Valve manholes, installation of Valves and fittings - Reinstatement of asphalt roads and pavements in overall length of aprox. 10.000 m’ - Supply and installation of valves, fittings

Sewerage Network Component

Construction of approximately 4.500m’ of Main Collectors, 21.000m’ of secondary system plus branches for house connections diameter DN 250, DN 400 and DN 630. Rehabilitation of the existing Sewerage Pumping Station

The Work Contract is based on the FIDIC 1999 (Red Book)

Jun 2006Dec 2007

Project Manager

BeB Ingg. S.p.A.

Sewerage Project in the City of Korça (Albania) - Sewage Construction / Construction of Stormwater Tanks - Financed by KfW - value 3,2 million euro. Construction of :90 concrete shafts -2 stormwater tanks - 1 syphon - 1 culvert (tot. 2.400 c.m. of concrete). Total of sewage pipeline (concrete and HDPE) : 5,7 km.Mechanical installations.

Work Contract based on the FIDIC 1999 (Red Book)

Dec 2005Dec 2007

Project Manager

BeB Ingg. S.p.A.

Municipal and Environmental Action Programme - MEAPI.20

Water Distribution Network Rehabilitation - LOT 5 Strumica

Financing authority: European Bank for Reconstruction and Development (EBRD)

Contract value (Euro): 852.000

Construction of a main and secondary water supply pipelines in overall length of approximately 25.000 m’ of HDPE 100 water mains diameter from DN 90 to DN 140 mm, MDPE 80 water mains diameter from DN 32 to DN 63 mm and execution of approximately 500 new service house-connections.

Pipe laying of4.600 m’ HDPE 100 pipes DN90, PN 10 bar

Pipe laying of3.300 m’ HDPE 100 pipes DN 110, PN 10 bar

Pipe laying of500 m’ HDPE 100 pipes DN 140, PN 10 bar

Pipe laying of6.900 m’ MDPE 80 pipes DN32, PN 10 bar

Pipe laying of 10.100 m’ MDPE 80 pipes DN63, PN 10 bar

Construction of R.C. Air Valve manholes, installation of Valves and fittings

Construction of R.C. Isolation Valve manholes, installation of valves and fittings.

Construction of R.C. Wash Out Valve manholes, installation of Valves and fittings

Reinstatement of asphalt roads and pavements in overall length of approx. 10.000 m’

Final Design and As-built drawings

Supply and installation of valves, fittings

Work Contract based on the FIDIC 1999 (Red Book)

Feb 2006Dec 2007

Project Manager

BeB Ingg. S.p.A.

Municipal And Environmental Action Programme - MEAPI.20

Water Distribution Network Rehabilitation - (Lots 1a, 2a, 3, 4)

Financing authority: European Bank for Reconstruction and Development (EBRD)

Contract value (Euro): 3.600.000

Lot 1a – Stip: execution and completion of the laying of approx 8.000 m’ of HDPE 100 water mains diameter from DN 90 to DN 280 mm and execution of approx 500 service house-connections.

Lot 2a – Veles: execution and completion of the laying of approx 4.000 m’ of HDPE 100 water mains diameter from DN 90 to DN 280 mm and execution of approx 300 service house-connections.

Lot 3 – Strumica: execution and completion of the laying of approx 24.000 m’ of HDPE 100 water mains diameter from DN 90 to DN 355 mm and execution of approx 600 service house-connections

Lot 4 – Kumanovo: execution and completion of the laying of approx 28.000 m’ of HDPE 100 water mains diameter from DN 90 to DN 355 mm and execution of approx 1.100 service house-connections.

Construction of a main and secondary water supply pipelines in overall length of approximately 64.000 m’ of HDPE 100 water mains diameter from DN 90 to DN 355 mm, MDPE 80 water mains diameter from DN 32 to DN 63 mm and execution of approximately 2.500 new service house-connections.

Pipe laying of11.600 m’ HDPE 100 pipes DN90, PN 10 bar

Pipe laying of2.900 m’ HDPE 100 pipes DN 110, PN 10 bar

Pipe laying of7.100 m’ HDPE 100 pipes DN 200, PN 10 bar

Pipe laying of500 m’ HDPE 100 pipes DN 280, PN 10 bar

Pipe laying of2.400 m’ HDPE 100 pipes DN 355, PN 10 bar

Pipe laying of15.500 m’ MDPE80 pipes DN32, PN 10 bar

Pipe laying of24.000 m’ MDPE80 pipes DN63, PN 10 bar

Construction of R.C. Air Valve manholes, installation of Valves and fittings

Construction of R.C. Isolation Valve manholes, installation of valves and fittings.

Construction of R.C. Wash Out Valve manholes, installation of Valves and fittings

Reinstatement of asphalt roads and pavements in overall length of aprox. 47.000 m’

Final Design and AS-built drawings

Supply and installation of valves, fittings.

Work Contract based on the FIDIC 1999 (Yellow Book)

Jun 2006Mar 2007

Project Manager

BeB Ingg. S.p.A.

Construction of Water Supply System in Srbinovo, Municipality of Gostivar – Program CARDS 2004

Financing authority: European Agency for Reconstruction (EAR) - Contract value (Euro): 126.000

Construction of a main water supply pipeline in overall length of 1.862 m connected to the existing water supply pipeline in Srbinovo:

Construction of a water supply pipeline of HDPE 100 pipes dia 160mm, 6 bars,in length of 1.412m,

Construction of water supply pipeline of HDPE 100 pipes dia 160 mm, 10 bars, in length of 450 m

Construction of 4 air valve manholes including valves, fittings, etc

Construction of 1 isolation valve manhole including valves, fittings, etc

Construction of 2 washout manholes including all valves, fittings, flap valves,

Construction of one water reservoir with capacity of 150 m3including all necessary valves, fittings, etc

Construction of one water Intake structure including all necessary valves, fittings, etc

Installation of Chlorinating System

Connection to local electrical network and complete internal Electrical Installation for the Reservoir

Reinstatement of asphalt roads and pavements in overall length of aprox. 1.00 km

Final Design and AS-built drawings

Supply and installation of valves, fittings

Sep 2005Aug 2006

Project Manager

BeB Ingg. S.p.A.

Construction of Sewerage Scheme in Municipality of Delcevo – Program CARDS 2002

Financing authority: European Agency for Reconstruction (EAR) - Contract value (Euro): 307.000

Construction of a sewerage scheme in overall length of 4.358 m

Construction of a sewerage scheme of HDPE pipes dia 200 mm in length of 2.082 m, dia 250 mm in length of 2.035 m and dia 315 mm in length of 241 m.

Construction of a 105 precast reinforces concrete manholes with 1.0 m dia and different high

Construction of a Waste Water Treatment Plant for 800 equivalent inhabitants with a total daily inlet of 160 m3 /day, including all related structure

Construction of a wire mesh fence around the WWTP with overall length of 140 m

Construction of new 10/0,4 kV tower substation equipped with 50 kVA transformer and 10 kV connection.

Reinstatement of asphalt roads and pavements in overall length of approx. 900 m’

Final Design and AS-built drawings

Supply and installation of valves, fittings

Mar 2006Mar 2006

Project Manager

BeB Ingg. S.p.A.

Construction of Water Supply System in the Municipality of Bitola – Program CARDS 2003

Financing authority: European Agency for Reconstruction (EAR) - Contract value (Euro):237.000

Construction of main water supply pipeline in overall length of 2.880 m tapped to the existing water supply pipeline in the city of Bitola:

Construction of a water supply pipeline of HDPE 100 pipes dia 225mm, 12.5 bars,in length of 1720m,

Construction of water supply pipeline of HDPE 100 pipes dia 225 mm, 10 bars, in length of 1.160 m

Construction of 8 air valve manholes including valves, fittings

Construction of 1 isolation valve manholes including valves, fittings

Construction of 8 washout manholes including all valves, fittings, flap valve, soak away pits

Construction of 46 m3 concrete horizontal and vertical anchor blocks

Construction. of pipeline protective r.c. sills for stream crossings in overall length of 61.45 m

Construction of one water reservoir with capacity of 135 m3including all necessary valves, fittings etc.

Construction of protective wire-mesh fence with entrance gate in overall length of 80 m

Reinstatement of asphalt roads and pavements in overall length of approx. 1.800 m’

Final Design and AS-built drawings

Supply and installation of valves, fittings

Dec 2002Mar 2006

Project Manager

BeB Ingg. S.p.A.

Municipal and Environmental Action Programme - MEAP

Struga and Ohrid Water Supply Project

Financing authority: KfW Bank & European Bank for Reconstruction and Development EBRD

Contract value (Euro): 6.036.000

Improvement of the existing Water Supply System through civil and electro-mechanical works for the construction of:

Reinforced Concrete Reservoirs : Struga

Zagracani H.L. (New) : no. 2x2.250 = 4.500 m3 capacity

Zagracani L.L. (New): no. 1x100 = 100 m3 capacity

Velesta (Rehabilitation) : no. 2x300 = 600 m3 capacity

Reinforced Concrete Reservoirs : Ohrid

Orman H.L. (New) : no. 1x100 = 100 m3 capacity

Orman L.L. (New): no. 1x1000 = 1000 m3 capacity

Studencista H.L. (Rehabilitation) : no. 1x3.500 = 3.500 m3 capacity

Studencista L.L. (New) : no. 1x1000 = 1.000 m3 capacity

Bej Bunar (New) : no. 1x100 = 100 m3 capacity

Rehabilitation of 11 existing pumping stations with capacity from 5 to 75 l/sec., head from 66 to 180 m, power from 15 to 120 Kw

Laying of approximately 50.000 m’ of pipelines, HDPE materials DN100 to DN600, PN 6, PN 8, PN10 and PN16

Construction of Break Tank Chambers no. 11x10 = 110 m3 capacity

Construction of R.C. Air Valve manholes, installation of Valves and fittings

Construction of R.C. Isolation Valve manholes, installation of valves and fittings.

Construction of R.C. Wash Out Valve manholes, installation of Valves and fittings

Reinstatement of asphalt roads and pavements in overall length of approx. 20.000 m’

Final Design and AS-built drawings

Supply and installation of valves, fittings

Work Contract based on the FIDIC Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer, First edition, 1999 (Red Book)

Jan 2000Dec 2002

Team Leader

Studio Valle Progettazioni - Roma

Italian Embassy – Italian Cooperation (Ufficio Cooperazione e Sviluppo) – Final Design of the Hospitals of Elbasan and Gramsh

Co-ordination of all the Technical Disciplines and with the Client. Technical Assistance inside the Tender Commission for the contracts concerning the Definitive Design and the Construction Works.

Sep 1999Sep 2002

Resident Engineer - Team Leader

Studio Valle Progettazioni - Roma

Consulting Services for the Supervision of Construction for the New Border Crossing Facilities at Tri Urat and for the Charcova-Tri Urat Access Road. PHARE Project AL 9402-03-01/T16

Value 3,7 million euro.

Complete Service in the Administration of the Construction Contract and in the Supervision of the Works on site. Construction of 7 Km of road, including culverts and 2 bridges. Construction of the New Border Crossing Post of Tri Urat (600 sq.m.) : supervision of all the civil works, electrical and mechanical installation

Work Contract based on the FIDIC Red Book

Jan 2002Jun 2002

Contract Engineer

World Bank Group

Office Expansion and Reconfiguration Project – Tirana 2000

WORLD BANK GROUP Country Office – Tirana (Albania)

Supervision of the preparation of the Design, the Technical Specification, the tender procedures and selection of the Contractor for of the full rehabilitation of the Albania’s Country Office of the World Bank

Jan 2000Mar 2015

Technical Advisor

Italian Embassy in Tirana  - Italian Embassy in Macedonia

Several certification of works performed by Italian companies in Albania (among the others : company Murgo "Works for installation of the technological plants for the Department of Cardiology Surgery and Intensive Therapy of the University Hospital “Mother Teresa” of Tirana; company Meridiana "Works for the completion of 1st Lot of the hospital “Nostra Signora del Buon Consiglio” of Tirana"; company COSMAR "Reconstruction of the Ferry Terminal in the Port of Durres"; company Falcione " Works for structural and architectural rehabilitation of the headquarter ofBanca Italo Albanese Sh.A. of Tirana").

Project for the risks’ preventionin the Italian embassy’s UTL in Tirana and in the Consulate in Valona

19961998

Project Manager

Taloca Srl

Residential, Commercial and Office Constructions – for the TALOCA S.r.l. in Moscow – Russia and Baku – Azerbaijan – Economic Feasibility Studies, Detailed Co-ordination of the Architectural and Engineering Design and Construction Contract Documentation and Technical Co-ordination during the constructions.The services performed included in addition to the “On Site” project management duties, the purchase and customs proceedings and formalities regarding the construction works.The responsibilities included the direct supervision of several ex-patriots and and all thelocal staff members.

Among the others : - Construction of the residence of Farko Group Director in Moscow (500 sq.m. villa)

- reconstruction of Farko Group offices in Baku - Adzerbaijan (300 sq.m.)

- reconstruction of flats in Moscow

19951996

Senior Executive

Intertransports Centre

European Union TACIS Programme in co-operation with the Forest Ministry of the Russian Government – for the re-organisation of the transportation of forest products for five principle regions of Russia, – Economic Feasibility Studies, Detailed Co-ordination of the Engineering Design and Construction Contract Documentation and Technical Co-ordination during the construction of this completely new network of service roads.The services performed included in addition to the “On Site” project management duties, the instruction of seventy Russian Technicians (Forest Directors and Managers) for a period of two months in Russia and one week in Italy.

19911995

Site Engineer

Group Inter

Detailed Design , complete supervision, defect liability period of the construction of a 15,000 sq. m. industrial complex used for the production of forest products ranging from windows and doors to structural grade lumber and laminated beams, – Economic Feasibility Studies, Detailed Co-ordination of the Engineering Design and Construction Contract Documentation and Technical Co-ordination during all the phases of the construction of this "turn key" completely new industrial complex.