Senior Planning Engineer

Urbacon Contracting & Trading
- Building construction baseline, revised and recovery programmes for projects along with narrative basis of programme highlighting the method of construction and potential risks in the project. - Submitting daily, weekly, monthly progress reports for client, head office and project manager. - Preparing KPIs, manpower & materials histograms, equipment deployment chart, cash flow, progress S-curves, progress charts and updating the same - Writing and replying to client’s and subcontractors correspondences. - Following up and monitoring shop drawings, Material Approval Requests and long lead items schedules. - Following up and checking progress payments and material on site payments. Achieved projects: - Lekhwiya Sport Stadium, Doha - Qatar. - Umm Garn Complex, Doha - Qatar.
Apr 2009 - Apr 2012

Planning Engineer

Halcrow
- Monitoring and checking construction baseline, revised and recovery programmes for contractors - Monitoring and checking contractor’s monthly progress reports including manpower & equipment histograms, cash flow, progress S-curves, progress charts. - Submitting weekly, monthly progress reports for client, head office and project manager. - Writing and replying to client’s and contractors correspondences. - Monitoring and checking shop drawings, Material Approval Requests, RFI’s and long lead items logs. Achieved projects: - Yasmeen Rotana Hotel, Damascus – Syria. - Centro Rotana Hotel, Damascus – Syria. - Cordoba Residential Complex, Damascus – Syria. - Nobles 101 Development, Damascus – Syria. - The Eighth Gate of Damascus, Damascus – Syria.
Feb 2008 - Apr 2009

PCS Engineer

2p2c Project Control Services
- Project work breakdown structure & ID structure. - Construct detailed logical Baseline program with critical path analysis. - Presenting schedules of work with visual aids such as bar charts and procedures diagrams. - Optimization of project resources. - Manpower calculations & Histograms. - Cash flow Loading & S- Curves. - Key Performance indicator (KPI). - Issue multi-level reports. - Providing advice and support on the development of specific systems. Achieved projects: - The Binary Tower@ Business Bay, Dubai- UAE. - Ocean Heights Tower, Dubai- UAE. - Infinity Tower, Dubai- UAE. - Forbidden City - Package 2, Dubai- UAE.
Oct 2005 - Jan 2008

Site/Project Engineer

Arabtec Construction LLC
- Monitoring and reporting progress. - Managing site teams. - Checking shop drawings to ensure conformity. - Supervising sub-contractors and manpower. - Liaise between consultant, QC and site engineers. - Liaise between suppliers and the company. Achieved projects: - Burj Khalifa (Burj Dubai), Dubai- UAE. (Project Engineer) - Palm Jumeirah Island, Dubai- UAE. (Project Engineer) - Dubai International Financial City (DIFC) -Gate Village, Dubai- UAE. (Site Engineer)

Education

Education
2001 - 2005

Bachelor

Damascus Univercity

Skills

Skills

Public-private Partnerships

Microsoft Project

Construction Engineering

Process Scheduler

Construction Cost Control

Schedule Control

Project Coordination

Cost Planning

WBS

Earned Value Management

Progress Monitoring

High Rise

P3

Value Engineering

Structural Engineering

Contractors

Cost Control

Concrete

Engineering

Subcontracting

Contract Management

CPM Scheduling

Software Project Management

AutoCAD

Civil Engineering

FIDIC

Construction

Construction Management

Project Planning

Project Control

MS Project

Primavera P6