Download PDF

Work experience

POSCO

CONSTRUCTION ASSIST MANGEER

Site Manager

SHAM Company
Site manager with in Kirkuk the project was new Road between Kirkuk and Shawan city its belong 40KM and all small bridge and derange system the rain water My Job was to control all activates and calculate the quantity of earthwork and all concrete work and modify the design 7~

1927Present


20142015

POSCO
20142015

POSCO

20132014

Chief of Engineering

SsangYong South Korea Company in sulimanyia city
Chief of engineering and design department with halbja city the project was water supply improvement in Kurdistan region and distribution new pipeline 300km My job wasprepare the shop drawing for all zones and calculate the quantity of pipe, survey some zone, design new alignment for our pipeline, and submit to the consultant 11~
20122013

Engineer

P.E. W.(POWER ENG. WORLD)
FROM CO., Hyunday engineering corporation Working as construction Eng in Taza gas power plant In KIRKUK(290 MG) including GT foundation, central control building, water treatment, fire fighting, switch yard, oil pipe and water trenches, water tank turbine alignment embed part setting leveling and setout street and walk way and all steel structure work…. etc. 9~ 10~
20072008

Site Engineer

AL-Iraqia
From site engineer with local contactor company in north oil company Kirkuk city when we fixed 4 big oil tank and installing new oil pipe line5 km and 2 control room building and 270 electric pole 33 kv from k1 to arafa city From2008 to 2010
20052007

Site Engineer

From Site engineer with Bechtel international system in Kirkuk Taza power plant GAS TURBIN POWER PLANT(125+60MW) and all QC work and inspection and all construction work and planning and quantity survey My responsibility was Turbine foundation and Stack Transformer Switchyard Underground system Trench system 5~ 6~

Education

20042005

Kirkuk Technical College

Skills

Certifications

Text Section