Abdullah Faisal Al-Muaigel

Work History

Work History
Nov 2012 - Present

Project Engineer (III)

Saudi Arabi Oil Company (ARAMCO)

- Determining objectives and evaluating alternatives.

- Defining scope.

- Developing and monitoring schedules.

- Estimating and monitoring costs.

- Engineering and designing equipment, piping and process flow.

- Preparing specifications for construction and equipment purchases.

- Managing equipment procurement.

- terms and conditions.

- Supervising and planning jobs.

- Interfacing with operations and regulatory agencies.

- Managing the turnover, startup and maintenance of facilities.

 

 

Acting as Clint Rep. for several Project inside Abqaiq Plants:

 

Upgrade Power Transmission System

This project addresses the existing electrical network deficiencies and improves high-voltage power supply reliability into North Ghawar Producing Facilities: ABGOSP-2, ABGOSP-3, and ABNWIP.  Abqaiq Plants scope of this project is to expand Abqaiq Plants 69 kV outdoor substation 50 switch-yards by installing two new breaker-and-a-half bays with hybrid circuit breakers and all associated control and protection equipment. The LSTK “Lump Sum Turn Key” contract was awarded to EPC “Energy Power and Contracting” company. (Cost: $98MM)

 

Replace Medium Voltage Cables (PILC), Abqaiq Plants

This budget item for the replacement of medium voltage cables at Abqaiq Plants to improve the plants’ reliability. It is proposed to replace 16,700 meters of 13.8kV PILC (Paper Insulated Lead Covered) cables supplying power to 12 substations.   (Cost: $ 32MM)

Upgrade Buildings for Risk Mitigation

This project was submitted to provide buildings with pressurizing system and toxic gases detection system. This project will upgrade seventy two (72) buildings which are subjected to a higher risk. Five (5) of these buildings require mitigation from explosion hazard, seventy (70) from fire or flammable gas related hazard and twenty-one (21) from toxic gas ingress hazard. (Cost: $ 32MM)

Abqaiq Plants 3rd Party Cogeneration Project

This project will support Saudi Aramco corporate strategy to maximize company energy efficiency. BI-10-00992 is a 3rd party cogeneration facility. Power Systems is the proponent of this facility. The Energy Conversion Agreement (ECA) was signed between Saudi Aramco and Consortium headed by Marubine Company of Japan. The Consortium awarded the LSTK to SAMSUNG. Two gas turbine generators with their HRSGs will be constructed at the Cogeneration Site (North of APS-7). The facility will supply approximately 1200 MMPPH of high pressure steam to Abqaiq Plants and export 300 MW of power to Saudi Electricity Company Substation # 49. This project will increase Abqaiq Plants overall steam efficiency from 64% to 81%. (Cost : $235MM)

 

Apr 2013 - Oct 2013

Project Engineer ( III)

Yanbu Aramco Sinopec Refinery Project (YASREF)

Assigned as lead Project /Construction Engineer handling construction activities for BEU Unit. Filed interface coordinator and EPC-3 Civil Scop.

Nov 2010 - Mar 2012

Project Engineer (III)

ARAMCO Over Seas Compnay

Assigned as a Project Engineer in Naphtha Hydrotreating Unit working with EPC contractor in South Korea during this assignment the following tasks were handled

- Naphtha Hydrotreating Unit project engineering

- Engineering and Construction interfaces coordination  

- Constructability program coordination

- Involved in the following technical review / activities

* 90 days design verification period

* 30 % , 60 % , 90% 3D design molding review  

* 40% , 60% Naphtha Hydrotreating Unit design review

* Primary and supplementary HAZOP

* Change Orders

Aug 2007 - Oct 2010

Project Enginner (IV)

Saudi Arabia Oil Company ( ARAMCO)

Assigned as Electrical Project / commissioning Engineer at Water Injection Plants Upgrade Division BI-03451(Under Khurais Project Department) – I was Covering Several Locations:

- Uthmaniyah Water Supply Station (UWSS)

- Haradh Gas Oil Separation Plant (HGSOP)

- Ain Dar Water Injection Plant (ADWIP)

- Hawiyah Center Water Injection Plant (HCWIP).

My role was to lead all commissioning activities and sign the final mechanical completion certificates

Sep 2006 - Jul 2007

Electrical Engineer (IV)

Sadui Arabia Oil Company (ARAMCO)

Provide technical services to company electrical units and handling facilities as well as coordinating engineering work to solve major problems on quality and design in electrical circuits. This includes maintaining up-to-date comprehension of all electrical design problems and operating difficulties. Plan, schedule and provide work direction as required for preparation of designs, processes, reports, correspondence and related data and assure the efficiency, adequacy and conformance to overall objectives of all phases of very complex electrical engineering problems. Support the development, and formulate the basis for engineering studies in any of several basic or special engineering fields by analyzing and evaluating data, including scope, effect on existing installations and economic value. Initiate detailed work outline and make decisions as to basic approaches, processes and/or equipment. Perform work and/or delegate work to other engineers for final development of specialized or technical proposals and proposed projects. Long range planning and reviewing cost estimates. Discuss, coordinate and resolve problems with personnel throughout Saudi Aramco and subsidiaries and outside contractors. Act as technical consultant when required.

Education

Education
Mar 2014 - Present

MSc, Project Management

University Of Liverpool (online Degree)

Certifications

Certifications
Mar 2014 - Mar 2019

PRINCE2® Foundation in project management

AXELOS
Mar 2014 - Mar 2019

PRINCE2® Foundation in project management Practitioner

AXELOS
Jun 2014 - Jun 2017

Risk Management Professional (PMI-RMP)

Project Management Institute
Sep 2013 - Sep 2016

Project Management Professional (PMP)

Project Management Institute